14 September 2011

Week 22

We are so impressed with how much has been done this week and very happy with how it's all coming together =)

The tiling is finished

Kitchen splashback


Ensuite
Laundry
Bathroom

Painting has also been completed





We had some deliveries
Pavers!!

An attempt to see how the colours look together

Kitchen appliances and gas HWS

Dunnies!

Both the Plumber and Electrician have installed their final bits and pieces and we also have door handles (some pics through windows for now)




Hmmm......not much left to do =)
Exciting!!

29 August 2011

Week 20

We are well and truely tightly locked out now! The only way to get in is to go when the tradies are there!

Lucky for us, there were plenty of opportunities this week =)

Lots of exciting progress!!!

Painting undercoat to door frames, doors, ceilings and cornices......




Deliveries......

Tiles

Bath, basins and ensuite benchtop

Ensuite cabinets

Overhead cabinets, rear kitchen bench and sink
Kitchen island cabinets
Rear kitchen cabinets and kickboards

We also met with our supervisor this week. If all runs smoothly and to schedule, we hopefully will be meeting him again the last week of September/early October for our Pre-handover......YAY!! While there we got to check out our installed cabinets =)......

Ensuite cabinets with benchtop, basins and tapware
Bathroom cabinets also all done and the bath in place

Showers don't look so small now with the white waterproofing applied
Laudry cabinets with benchtop, trough and tapware
The KITCHEN =)

With overheads, benchtops, kickboards, sink and tapware!
Island bench with spaces for microwave and DISHWASHER =)

Rear island bench with spaces for 900mm oven and cooktop

I just want to rip that blue stuff off the benches lol, very happy with our choices so far =)

12 July 2011

Week 13

We have reached what should be the half way point this week......yay!!
The house has been buzzing with tradesmen and there has been lots of progress. The roof frame was completed, fascias installed, blue thingies put on (have no idea what they are lol), eaves and ceilings to the Alfresco and Garage are up, the plumbers got busy installing all the pipes and the sparkies chased (?) the walls ready for wiring =)
Alfresco ceiling and eaves
Fascia and the blue thingies lol

Roof frame is complete


Ensuite

Kitchen

Bathroom
Outside tap

The brickie team also came back and finished the nib wall to the robe in Bed 4 =)


Not long now before we get a roof cover......exciting!!