18 July 2011

Week 14

The electricians have been in to run their cables and install the power point boxes. We opted for an Intelligent Homes Package so there were a few extra cables to look at =)
Cables and power boxes for the GPO's

Part of our IH package...for outside speakers and TV

Our smart wiring panel will be here...lots of cables!
Gutters are on and downpipes to the rear and sides of the house have also been installed.
Gutters =)
And again!


Downpipes delivered...
and installed!
 
And last but not least we had an exciting delivery at the end of the week......our colorbond =)
Colorbond "Monument"
The "hats" for our exhausts

12 July 2011

Week 13

We have reached what should be the half way point this week......yay!!
The house has been buzzing with tradesmen and there has been lots of progress. The roof frame was completed, fascias installed, blue thingies put on (have no idea what they are lol), eaves and ceilings to the Alfresco and Garage are up, the plumbers got busy installing all the pipes and the sparkies chased (?) the walls ready for wiring =)
Alfresco ceiling and eaves
Fascia and the blue thingies lol

Roof frame is complete


Ensuite

Kitchen

Bathroom
Outside tap

The brickie team also came back and finished the nib wall to the robe in Bed 4 =)


Not long now before we get a roof cover......exciting!!

02 July 2011

July 2011 - Week 12

Brickies finished, cleaned up, packed up and left Monday......and they left it looking spotless, even swept the floor! Unfortunately they still forgot Bedroom 4's robe recess, but our SS and his brickie team had already scheduled a time for them to come back before I'd even contacted him.

Finished fridge recess (and the broom)

Our Living areas looking very clean


The very same day we had some more deliveries for our roof!

To our surprise, the tradies made a start on our roof frame in the wind and pouring rain......impressive!



High ceilings to our Living areas =)

Our Alfresco has high ceilings too =)


Our future outdoor entertaining area


Week 11

Brickwork is finished! Well......almost! Half a fridge recess wall and a wall for Bedroom 4's robe recess is all that is left to be done and the brickies are finishing that up Monday of next week. The two of them did a great job and it all looks very neat.

Let me take you on a tour......

Sorry nowhere to park yet. Scaffolding and beams for the next stage are in the way=)

Entry
Entry again from the inside. 1st door to Bed 1 & opening to living area.
















Bed 1
Bed 1 with opening to WIR and Ensuite
Robe
Ensuite
Ensuite WC



Theatre off the Entry
Theatre again
Living areas
Kitchen. Opening to the left leads to Hallway, door to WIP
Pantry
Bed 2
Hallway
Laundry
Laundry again with WIR & WC
WC
WIL
Bathroom
Bed 5
Bed 3
Bed 4






























Out the big stacker/slider doors to the Alfresco & future patio

Looking though the doors to our living areas

Looking through our double slider into kitchen

From end of the Alfresco looking through triple stacker to Living areas
  Thankyou for taking the tour =) I apologise in advance, you are probably going to see it all again as our home evolves!!